JPMorgan and Mitsubishi UFJ Financial Group are set to lead a $22 billion loan facility to finance Vantage Data Centers' ambitious $25 billion data centre campus in Shackelford County, Texas ...
At a quarterly meeting of the Baton Rouge Industrial Group in Donaldsonville, Ascension officials and Gov. Jeff Landry promoted planned industrial projects. Outside, some residents criticized the ...
Louisiana utility regulators approved a plan Wednesday, August 20, 2025 to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for ...
The Louisiana Public Service Commission met with Entergy officials regarding a vote to pass a settlement that would fund a gas plant for the Richland Parish Meta Data Center project. Frontline workers ...
The Louisiana Public Service Commission met with Entergy officials regarding a vote to pass a settlement that would fund a gas plant for the Richland Parish Meta Data Center project.
The Louisiana Public Service Commission is approving several Entergy projects that are supposed to ramp up power generation ...
The Louisiana Public Service Commission (PSC) will outline its after-action findings in Baton Rouge following the outage, ...
The Louisiana Public Service Commission voted 4-1 to approve Entergy’s plan to build three natural gas power plants for Meta’s $800M data center in Richland Parish ...
Louisiana Public Service Commissioners voted four to one to approve Entergy’s three new gas plants to power Meta’s largest-ever data center.
The facility is set to require more than double the energy needed to power the entire city of New Orleans during peak summer heat.
The Louisiana Public Service Commission approved a plan to install three turbine generators that will power Meta’s new data center in Richland Parish. The 4-1 vote ...
The Louisiana Public Service Commission gave Entergy the green light to construct three power plants in preparation for the ...